Works & Road Closures List View
Townsville City Council is committed to delivering well-maintained infrastructure and efficient transportation systems, with over $400 million being invested in roads and transport management, open spaces, water, and wastewater management this financial year.
This page contains works and road closures currently underway or planned in a screen reader friendly list. To view the interactive map version, visit Works & Road Closures.
For State Government road works and closures, visit Queensland Government Traffic and Travel Information.
Disclaimer: Information should be used as a guide only. Dates and times relating to the works are estimates and may be impacted by weather and project conditions.
Coastal Management
Horseshoe Bay Beach, Horseshoe Bay – Coastal Management Recovery Works
Date published: Wednesday 16 April 2025
Work boundaries: Horseshoe Bay Beach, Horseshoe Bay
Estimated start: Wednesday 23 April 2025
Expected duration: One (1) week
Normal work hours: 6am to 6pm Monday to Thursday. No work will happen over the ANZAC weekend. The schedule is dependent on tidal conditions and machinery availability.
Townsville City Council is continuing coastal management recovery works, which involve reshaping the sand along the foreshore that is most vulnerable to erosion.
Council has received recovery funding to undertake these works. As part of the funding agreement, the DRFA requires Council to complete these works by the end of April 2025.
This project is part of Council’s ongoing commitment to environmental management, which identifies the need for coastal works to address and mitigate the effects of erosion caused by recent weather events.
As part of these works, Council will replenish sand at the base of palm trees along the foreshore, with only small sections of the beach closed at any given time.
We are working with the Surf Life Savers to ensure minimal impact on the stinger net. Although machinery will be in operation, the larger pieces of equipment regularly employed for sand renourishment will not be required. If you live in or are travelling through the area, you may experience:
- sections of beach foreshore closed at one time within the area illustrated
- light machinery and vehicle movement
- increased levels of dust, noise, and vibrations.
Council will close only small sections of the beach and foreshore at a time to allow machinery to work on the beach. Once we complete work on one section, we will move to another area to address erosion around the palm trees.
The eastern side of the boat ramp, which faces the businesses, will still have accessible sections of the beach for the public. However, the small sections where machinery is operating will be temporarily closed for public safety.
Assistance provided through the jointly funded Australian and Queensland Government Disaster Recovery Funding Arrangements (DRFA).
Nelly Bay Beach, Nelly Bay – Coastal Management Recovery Works
Date published: Friday 4 April 2025
Work boundaries: Nelly Bay Beach, Magnetic Island
Estimated start: Monday 7 April 2025
Expected duration: Two (2) weeks
Normal work hours: From 6am to 6pm Monday to Saturday
What works are coming up?
Council is continuing coastal management recovery works, which involve reshaping the sand along the foreshore that is most vulnerable to erosion.
This project is part of Council’s ongoing commitment to environmental management, which identifies the need for coastal works to address and mitigate the effects of erosion caused by recent weather events.
What will the works include?
As part of this project, Council will undertake:
- Placement of sand to the most vulnerable sections of the foreshore for better stability and to protect assets
- Council staff will oversee and manage these recovery operations.
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- Partial beach closure as indicated overleaf
- Construction machinery and vehicle movement
- Increased levels of dust, noise, and vibrations.
Funding
This project is proudly funded by the Commonwealth and Queensland Governments through the Disaster Recovery Funding Arrangements and delivered in partnership with Townsville City Council.
Contact us
To find out more about these works or the project, please contact us on the details below.
Project Manager: Alma Ridep-Morris
13 48 10 (business hours)
enquiries@townsville.qld.gov.au.
Visit townsville.qld.gov.au and search: ‘Nelly Bay Coastal Management Works’.
Toomulla Beach, Toomulla – Coastal Management Recovery Works
Date published: Friday 4 April 2025
Work boundaries: Toomulla Beach, Toomulla
Estimated start: Monday 7 April 2025
Expected duration: Three (3) days
Normal work hours: From 6am to 6pm Monday to Saturday
What works are coming up?
Council is continuing coastal management recovery works, which involve reshaping the sand along the foreshore that is most vulnerable to erosion. This work also includes enhanced maintenance for the beach access paths adjacent to the Esplanade at Toomulla Beach.
This project is part of Council’s ongoing commitment to environmental management, which identifies the need for coastal works to address and mitigate the effects of erosion caused by recent weather events.
What will the works include?
As part of this project, Council will undertake:
- Placement of sand to the most vulnerable sections of the foreshore for better stability and to protect assets
- Council staff will oversee and manage these recovery operations.
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- Partial beach closure
- Construction machinery and vehicle movement
- Increased levels of dust, noise, and vibrations.
Funding
This project is proudly funded by the Commonwealth and Queensland Governments through the Disaster Recovery Funding Arrangements and delivered in partnership with Townsville City Council.
Contact us
To find out more about these works or the project, please contact us on the details below.
Project Manager: Ivy Summers
13 48 10 (business hours)
enquiries@townsville.qld.gov.au.
Visit townsville.qld.gov.au and search: ‘Toolakea Coastal Management Works’.
Drainage
Murray Street near Gregory Street, North Ward – Murray Street Culvert Upgrade
Date published: Tuesday 25 February 2025
Work boundaries: The culvert at the bottom of Murray Street nearing Gregory Street, North Ward.
Estimated start: Monday 3 March 2024
Expected duration: Six (6) weeks
Normal work hours: 6am to 6pm, Monday to Saturday
Council is preparing to recommence the culvert upgrade at the bottom of Murray Street nearing Gregory Street, North Ward.
These initial works are the first stage of Council's plans to upgrade Murray Street between Gregory and Victoria Streets.
This project is part of our Capital Works program, which aims to maintain Council’s assets to ensure the community's transportation, stormwater, water and sewerage needs are adequately met and continue to support the growth of our region.
As part of this project, Council will:
- upgrade the existing stormwater culvert at the Gregory Street intersection
- rehabilitate a portion of associated road immediately over the culvert
- remove vegetation within the works area as required.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
This project is proudly funded by the Queensland Government’s Works for Queensland program.
Environmental Restoration
Corica Crescent, Horseshoe Bay – Stormwater Drainage Drone Survey
Date published: Friday 4 April 2025
Work boundaries: Corica Crescent, Horseshoe Bay
Estimated start: Wednesday 9 April 2025
Expected duration: One (1) day
Normal work hours: 6am to 6pm Monday to Saturday
An aerial drone will be used to study the coastal sediment that may have collected within the Corica Crescent Stormwater Drainage system. This will help Council find ways to understand the impact from recent rainfall events on coastal sediment processes at Horseshoe Bay – and what management actions may be needed and can be prioritised.
This project is part of Council’s environmental plan, which highlights the need for coastal work to reduce erosion and strengthen the
coastline’s ability to handle future weather events.
The works will include:
- drone flyover
- coastal sediment study
If you live in or are travelling through the area, you may experience:
- whirring noises from drones
- drone lights in the sky
Drone Flight Path indicated in this map (along Apjohn Street and parallel to Corica Crescent):
Project funded by Townsville City Council.
Sherriff and Archery Park, Mundingburra – Riverine Site Maintenance
Date published: Monday 2 December 2024
Work boundaries: Sherriff and Archery Park riverbank
Estimated start: Monday 9 December 2024
Expected duration: Current stage: two (2) weeks. Project: until June 2026
Normal work hours: 6am to 6pm, Monday to Saturday
Townsville City Council is undertaking environmental restoration maintenance works along the riverbank to the Ross River within Sherriff and Archery Parks, Mundingburra.
Council began these works in October 2024. We expect maintenance weeding, mulching, and planting to take four months to complete and low-impact maintenance weeding to occur periodically until June 2026.
Council proposes dividing the site into two sections, restricting pedestrian access, and directing pedestrians to an alternative route.
We will close the pedestrian path within each section along the riverbank to suit works progress over the two week period.
Section one is from Sherriff Park to the Mabin Street Park entrance. Section two is from Mabin Street to the midpoint of Archery Park. You can still access the area through the Mabin Street park entrance.
Council will use safety bollards and flagging to mark the work areas and to ensure public safety.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Please note: Work will not be continuous across these months but in four stages.
Assistance provided through the jointly-funded Commonwealth-State Disaster Recovery Funding Arrangements (DRFA).
Event Road Closures
Mount Stuart Road, Murray – Road Closure
Date published: Wednesday 5 March 2025
Work boundaries: Mount Stuart Road, Murray
Estimated start: Monday 3 March 2025
Expected duration: Until it is safe to re-open
Council has closed Mount Stuart Road due to the potential risk of land slips following recent natural events. Updates on the road's reopening will be provided once safety concerns have been resolved.
This closure is part of Council’s commitment to maintain the road network, ensure safety, and support regional growth.
Works will include:
- closure of Mount Stuart Road, Murray
- land safety assessment
- mitigation works to increase safety.
If you live in or are travelling through the area, you may experience:
- no access into Mount Stuart Road, Murray
- increased levels of dust, noise, and vibrations.
Sooning Street, Nelly Bay – Sooning Street Bridge Closure
Date published: Tuesday 24 December 2024
Work boundaries: Gustav Creek on Sooning Street
Estimated start: Saturday 21 December 2024
Expected duration: Until further notice
Normal work hours: Closed until further notice
Recent heavy rainfall has damaged culverts under the bridge crossing Gustav Creek on Sooning Street and due to community safety concerns Council has closed the bridge.
A preliminary engineering assessment has been conducted and further investigations are required.
Council endeavours to have this additional inspection, and any necessary repairs completed as quickly as possible.
A detour is currently in place via Kelly St, Barton St and Mandalay Ave as signed to access Nelly Bay.
Ring Road, Annandale to Deeragun – Ring Road Cleaning
Date published: Friday 4 April 2025
Work boundaries: Ring Road, Annandale to Deeragun
Estimated start: Saturday 12 April 2025
Expected duration: One (1) night
The Ring Road will be closed for night cleaning between 10pm Saturday 12 April and 6am Sunday 13 April 2025, from the on and off ramps in front of Lavarack Barracks to the on and off ramps adjacent to the BIG4 Ingenia Holiday Park in Deeragun.
Traffic management will be in place with emergency vehicle access only during the closure.
Council thanks you for your patience and cooperation whilst these works are being undertaken.
The Strand, Townsville City – Anzac Day Road Closure - Townsville City
Date published: Saturday 19 April 2025
Work boundaries: The Strand and Oxley Street
Estimated start: 4:30am on Friday 25 April 2025
Expected duration: Until 9:30am on Friday 25 April 2025
Normal work hours: 4:30 to 9:30am
A temporary road closure to allow for the Anzac Day Dawn Service and Parade will be in place as follows:
- 4:30 to 7:30am: The Strand from Mariners Drive to Upper Wickham Street including joining side street intersections –Melton Terrace.
- 4:30 to 11am: Oxley Street between Mitchell Street and The Strand.
- 7:30 to 11am: The Strand from Landsborough Street to Upper Wickham Street including joining side street intersections – Stuart Street, Kennedy Street, Gregory Street, Oxley Street, Fryer Street, Mariners Drive and Melton Terrace.
Vehicles left within the area after the proposed closure will be towed at the owner's expense.
Ross River Road, Kirwan – Anzac Day Road Closure - Thuringowa
Date published: Saturday 19 April 2025
Work boundaries: Ross River Road from Bamford Lane to Thuringowa Drive
Estimated start: 8:30am on Friday 25 April 2025
Expected duration: 9:30am on Friday 25 April 2025
Normal work hours: 8:30am to 9:30am
A temporary road closure to allow for the Anzac Day Parade.
8:30 until 9:30am: Ross River Road from Bamford Lane to Thuringowa Drive/Riverway Drive intersection including joining side street intersections – Rolfe Street, Ridley Road and Hudson Street.
Vehicles left within the area after the proposed closure will be towed at the owner's expense.
General
Belgian Gardens Cemetery, Belgian Gardens – Improvement Works
Date published: Tuesday 15 April 2025
Work boundaries: Belgian Gardens Cemetery, Belgian Gardens
Estimated start: Tuesday 22 April 2025
Expected duration: Nine (9) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Council is preparing to undertake works for Stage Two of Burial Lawn 9 at the Belgian Gardens Cemetery, located at 62 Evans Street, Belgian Gardens.
This project will deliver 354 additional burial plots and additional ash interments, as well as offering pathway connections, seating areas with shelters, landscaping, turfing and irrigation to Burial Lawn 9 at the cemetery.
As part of this project, Council will:
- construct burial plots and ash interments
- install new turf and plant native trees
- undertake excavation and trenching work to install an efficient irrigation system connected to the upgraded water network
- construct a concrete pathway and sheltered seating areas.
If you are visiting the Belgian Gardens Cemetery, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- minor traffic delays and reduced speed limits.
Castle Hill Road, Castle Hill – Guardrail Inspection and Drone Survey
Date published: Tuesday 8 April 2025
Work boundaries: Castle Hill Road, Castle Hill
Estimated start: Thursday 15 April 2025
Expected duration: One (1) day
Normal work hours: 6am to 6pm Monday to Saturday
A guardrail inspection and an aerial drone survey will be carried out on Tuesday 15 April 2025 to inform the guardrail design along the road corridor. This will help Council improve commuter safety along Castle Hill Road.
This project is part of Council’s annual Guardrail Renewal program, which aims to ensure that guardrails are well-maintained and fit for purpose to offer improved safety to road users travelling adjacent to steep slope areas.
As part of this project, Council will undertake:
- drone surveying along Castle Hill Road from Stanley Street through to the summit of Castle Hill
- guardrail inspection
- traffic management
- surveyor work on the road.
If you live in or are travelling through the area, you may experience:
- whirring noises from drones
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
East of Southwood Road, Stuart – KZ Emergency Bypass Water Pressure Main Installation
Date published: Tuesday 1 April 2025
Work boundaries: East of Southwood Road, Stuart
Estimated start: Friday 4 April 2024
Expected duration: Two (2) weeks
Normal work hours: 11pm to 1am
Townsville City Council is preparing to install a new emergency bypass water pressure main underneath the Bruce Highway above the North Coast Railway crossing overpass and below the Stuart Landfill, east of Southwood Road.
Works will involve tunnelling the pipeline under the highway to limit the impact on road users. Once installed, the new bypass will eliminate the risk of pipeline failure underneath the highway, ensuring water supply reliability for downstream residents into the future.
In preparation for these works, Council will undertake a test shutoff that will result in a temporary water loss of approximately two (2) hours at night.
Suburbs affected by this water disruption include Nome, Alligator Creek, Mount Elliot, Elliot Springs, and Julago.
As part of these works, Council will:
- shut off the water and cut in the new connection points into the existing pipeline, each side of the highway
- tunnel the new pipe section underneath the highway
- excavate trenches and install the remaining pipeline
- connect the three sections of pipe together to provide a complete bypass of the existing pipeline
- reinstate and clean up the site.
It is essential to prepare by storing enough water in containers before this water disruption. When Council restores the water supply, it may initially appear discoloured. To address this, run taps until the discolouration disappears. Furthermore, Council recommends turning off automatic washing machines during this time.
Council will have complimentary bottled water for residents to collect at the Ampol service station in Alligator Creek and the BP service station in Elliot Springs.
We apologise for any inconvenience this work may cause and appreciate your patience.
Henry Lawson Street, Horseshoe Bay – Bridge Works
Date published: Tuesday 4 March 2025
Work boundaries: Henry Lawson Street Pedestrian Bridge, Horseshoe Bay
Estimated start: Monday 10 March 2025
Expected duration: Six (6) weeks
Normal work hours: 6am to 6pm Monday to Saturday
In response to feedback from the Magnetic Island community, Townsville City Council has conducted an additional structural assessment of the bridge, which provided the following recommendations:
- Maintain the current load limit of two (2) people.
- Conduct monthly visual inspections to monitor the condition of the structure and its temporary supports.
- Assess defects and corrosion every six (6) months.
Based on these recommendations, Council is working with a structural engineer to prolong the life of the pedestrian bridge and relocate existing services as a safety measure.
As part of this project, Council will:
- under bore the creek between Pacific Drive and Henry Lawson Street
- install a new water main, sewer pipes and a telecommunications conduit
- connect and commission the new services
- disconnect the existing services to the bridge
- reinstate the existing footpath and carpark.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane and road closures, minor traffic delays and reduced speed limits
- temporary closure of the adjacent pathway and carpark.
Nelly Bay Road, Nelly Bay – Guardrail Inspection and Drone Survey
Date published: Wednesday 9 April 2025
Work boundaries: Nelly Bay Road, Nelly Bay
Estimated start: Wednesday 16 April 2025
Expected duration: One (1) day
Normal work hours: 6am to 6pm Monday to Saturday
A guardrail inspection and an aerial drone survey will be carried out on Wednesday 16 April 2025 to inform the guardrail design along the road corridor. This will help Council improve commuter safety along Nelly Bay Road.
This project is part of Council’s annual Guardrail Renewal program, which aims to ensure that guardrails are well-maintained and fit for purpose to offer improved safety to road users travelling adjacent to steep slope areas.
As part of this project, Council will undertake:
- drone surveying along Nelly Bay Road from Sooning Street through to Birt Street
- guardrail inspection
- traffic management
- surveyor work on the road.
If you live in or are travelling through the area, you may experience:
- whirring noises from drones
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Saltwater Drive, Toomulla – Saltwater Drive Pump Station Upgrade
Date published: Friday 31 January 2025
Work boundaries: Saltwater Drive, Toomulla
Estimated start: Monday 10 February 2025
Expected duration: Four (4) months
Normal work hours: 6am to 6pm Monday to Saturday
Townsville City Council is upgrading the services to the existing pump station and constructing a new access road from Saltwater Drive, Toomulla. Council has identified the need to replace the water main and sewer rising main to the existing pump station and provide safer access to the existing facility.
Works include:
- construction of a new sewer rising main and water main
- replacement of electrical conduits
- construction of a new access road from Saltwater Drive to the pump station.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, minor traffic delays and reduced speed limits.
Sooning Street, Nelly Bay – Gustav Creek Structure Restoration Work - Culvert Removal
Date published: Friday 28 March 2025
Work boundaries: Sooning Street, Nelly Bay
Estimated start: Monday 31 March 2025
Expected duration: One (1) week
Normal work hours: 6am to 6pm Monday to Saturday
Townsville City Council is preparing to remove the damaged culverts that span Gustav Creek on Sooning Street in Nelly Bay. The work will involve excavators and heavy construction equipment to remove broken asphalt and debris washed downstream. Once the work site is clear, demolition of the culverts will occur.
Council plans to transport this material to the mainland via barge. Trucks will transport the material to the Magnetic Island ferry terminal, where barge services will operate to facilitate these works. The frequency of these activities will depend on barge availability.
As the work progresses, there may also be stockpiling of material on-site within the road closure area. These operations will depend highly on weather conditions like rain and high tides.
A local contractor, BMD Constructions, will deliver these works on behalf of Council.
As part of these works, Council will:
- clear away the broken asphalt and debris washed downstream
- remove remaining culverts
- take this material to the mainland using a barge.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits
- temporary loss of on-street parking.
Assistance provided through the jointly funded Commonwealth-state Disaster Recovery Funding Arrangements (DRFA).
Yule Street, Picnic Bay – Public Amenities Renewal
Date published: Monday 10 February 2025
Work boundaries: Yule Street Park, Picnic Bay
Estimated start: Monday 17 February 2024
Expected duration: Four (4) months
Normal work hours: 6am to 6pm Monday to Saturday
24/02/2025 - Palm Tree RemovalsCouncil's Principal Arborist recently conducted a thorough inspection of the Yule Street, Picnic Bay amenities renewal site and identified three Foxtail Palms for removal. The decision to remove the palms was made based on the certified arborist's report, with safety and the successful completion of the amenities renewal project as a priority. Council recognises the value of trees and is committed to minimising the impact of their removal by carefully planning replanting and proper placement. Works will take place on Monday 3 March 2025 and are expected to take one (1) day to complete, weather and project conditions permitting. As part of these works, Council will:
|
Council is carrying out a project to renew the public amenities in Yule Street, Picnic Bay on Magnetic Island.
This work is necessary as the existing amenities have reached the end of their useful life and are no longer compliant or functional.
The Magnetic Island community consultation in 2023 favoured upgrading the amenities at their current location.
Works will include:
- demolition of the existing amenities and septic system
- construction of new amenities and associated services including water and sewer connections
- site remediation for disturbed areas following construction.
The new public amenities will include unisex accessible and ambulant facilities.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations.
Temporary public amenities will remain during the construction period and will be removed once the new facilities are completed.
Works will not impact the bus stop. The playground may be affected at times.
This project is proudly funded by the Queensland Government’s Works for Queensland program.
Yule Street, Picnic Bay – Picnic Bay Reservoir Roof Replacement
Date published: Wednesday 26 February 2025
Work boundaries: Yule Street Park, Picnic Bay
Estimated start: Thursday 6 March 2025
Expected duration: Six (6) months
Normal work hours: 6am to 6pm Monday to Saturday
Council is replacing the roof of the Picnic Bay Reservoir, which provides potable water for Picnic Bay and parts of Magnetic Island.
To install the new roof, a crane will be used, and Ergon will temporarily disconnect nearby power lines for safety. The few affected properties will be notified in advance of any power outages or disruptions.
Local contractor A. Gabrielli Constructions is undertaking the work on behalf of the Council.
Works will include:
- removal of existing reservoir roof
- construction of new roof and associated framing, structure, and linings
- installation of ventilators, access ladders, and an access platform
- the disconnection of power lines, causing two power outages on separate days, two weeks apart, affecting only a small number of local properties.
- the first single-day shutdown will be on Tuesday 11 March 2025
- the second single-day shutdown will be on Tuesday 3 April 2025
- Ergon will be notifying the properties that will be affected.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- noise and odour, especially during power outages, caused by diesel generators
- increased levels of dust, noise, and vibrations
- power loss for a small number of properties twice, two weeks apart.
Parks and Playgrounds
Annandale Gardens Park, Annandale – Rubber Softfall Recovery Works
Date published: Thursday 17 April 2025
Work boundaries: Annandale Gardens Park, Annandale
Estimated start: Thursday 24 April 2025
Expected duration: Two (2) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Council is carrying out the replacement of rubber softfall on designated playground surfaces in Annandale Gardens Park, Annandale, which were affected by the recent weather event.
This recovery project is part of Council’s maintenance plan, which focuses on keeping our community assets and infrastructure in good condition and supporting regional growth.
Works will include:
- removal of the damaged rubber softfall and replacement with new softfall
- minor concrete work matched in neatly to existing infrastructure.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary closure of the playground asset affected by the works.
This project is proudly funded by the Australian and Queensland Governments through the Disaster Recovery Funding Arrangements and delivered in partnership with Townsville City Council.
Havenside Park, Garbutt – Rubber Softfall Recovery Works
Date published: Tuesday 15 April 2025
Work boundaries: Havenside Park, Garbutt
Estimated start: Tuesday 22 April 2025
Expected duration: Three (3) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Please note that due to ongoing weather events, Council has rescheduled the rubber softfall renewal works on designated playground surfaces in Havenside Park, Garbutt, which were affected by the recent weather events. The new timings are above.
This recovery project is part of Council’s maintenance plan, which focuses on keeping our community assets and infrastructure in good condition and supporting regional growth.
Works will include:
- removal of the damaged rubber softfall and replacement with new softfall
- minor concrete work matched in neatly to existing infrastructure.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary closure of the playground asset affected by the works.
This project is proudly funded by the Australian and Queensland Governments through the Disaster Recovery Funding Arrangements and delivered in partnership with Townsville City Council.
Strand Water Park, The Strand, North Ward – Electrical Works
Date published: Monday 14 April 2025
Work boundaries: Strand Water Park, The Strand
Estimated start: Late May 2025
Expected duration: Two (2) weeks
Normal work hours: From 6am to 6pm Monday to Saturday
What works are coming up?
Council is planning to undertake electrical maintenance works at the Strand Water Park, which includes installing a new electrical switchboard along with other required infrastructure and maintenance updates.
The Strand Waterpark, which is around 25 years old, has an electrical switchboard that is in poor condition and outdated. This switchboard powers the waterpark along with surrounding BBQs and lights, and needs to be replaced to provide efficient, sustainable service to the facility.
What will the works include?
- installation of a new energy-efficient electrical switchboard to provide direct sustainable service to the water park
- associated infrastructure and maintenance updates.
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- temporary closure of the Strand Water Park throughout works
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
Funding
Project funded by Townsville City Council.
Contact us
To find out more about these works or the project, please contact us on the details below.
Project Manager: Kim Smith
13 48 10 (business hours)
enquiries@townsville.qld.gov.au.
Visit townsville.qld.gov.au and search:
‘Strand Waterpark Electrical’.
Wheeler Park, Kirwan – Rubber Softfall Recovery Works
Date published: Wednesday 16 April 2025
Work boundaries: Wheeler Park, Kirwan
Estimated start: Wednesday 23 April 2025
Expected duration: Three (3) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Please note that due to ongoing weather events, Council has rescheduled the rubber softfall renewal works on designated playground surfaces in Wheeler Park, Kirwan, which were impacted by the recent weather events. The new timings are above.
This recovery project is part of Council’s maintenance plan, which focuses on keeping our community assets and infrastructure in good condition and supporting regional growth.
Works will include:
- removal of the damaged rubber softfall and replacement with new softfall
- minor concrete work matched in neatly to existing infrastructure.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary closure of the playground asset affected by the works.
This project is proudly funded by the Australian and Queensland Governments through the Disaster Recovery Funding Arrangements and delivered in partnership with Townsville City Council.
Woodbine Park, Annandale – Rubber Softfall Recovery Works
Date published: Tuesday 15 April 2025
Work boundaries: Woodbine Park, Annandale
Estimated start: Tuesday 22 April 2025
Expected duration: Two (2) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Council is carrying out the replacement of rubber softfall on designated playground surfaces in Woodbine Park, Annandale, which were affected by the recent weather event.
This recovery project is part of Council’s maintenance plan, which focuses on keeping our community assets and infrastructure in good condition and supporting regional growth.
Works will include:
- removal of the damaged rubber softfall and replacement with new softfall
- minor concrete work matched in neatly to existing infrastructure.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary closure of the playground asset affected by the works.
This project is proudly funded by the Australian and Queensland Governments through the Disaster Recovery Funding Arrangements and delivered in partnership with Townsville City Council.
Pathway Works
Gregory, Mitchell and Eyre Street, North Ward – Pathway Upgrade
Date published: Monday 24 March 2025
Work boundaries: Gregory, Mitchell and Eyre Street
Estimated start: Monday 17 February 2025
Expected duration: Six (6) months
Normal work hours: 6am to 6pm, Monday to Saturday
Townsville City Council is preparing to commence Phase Three of this project. Phase Three involves upgrading the pathway on the western side of Gregory Street, extending from Eyre Street to Mitchell Street. Council will deliver this phase of the project in three parts. The first section will begin in front of the Hotel Allen while it is closed for renovations. We will ensure that we maintain access to surrounding businesses during construction; however, customers and staff will temporarily lose on-street parking in the affected area.
Phase Three, Part One (fronting Hotel Allen, on the corner of Gregory and Eyre Streets) will start from Tuesday 25 March 2025 and is expected to take three (3) weeks to complete, weather permitting.
Works will include:
- traffic management and installation of temporary fencing
- removal of existing pavers and associated materials
- preparation of formwork and commencement of concrete pours
- application of two coats of sealer.
Once the work is completed, we will clean the site, remove the temporary fencing, and reopen the pathway and the road to the public.
Council assures businesses that access will remain open throughout the project. We will make every effort to minimise disruptions and keep stakeholders updated.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits
- temporary loss of on-street parking and disruption to the outdoor dining areas.
Proudly funded by the Queensland Government’s Works for Queensland program in association with Townsville City Council.
Roadworks
Cape Cleveland Road, Cape Cleveland – Roadworks
Date published: Tuesday 15 April 2025
Work boundaries: Cape Cleveland Road, Cape Cleveland
Estimated start: Tuesday 22 April 2025
Expected duration: Two (2) weeks
Normal work hours: 6am to 6pm, Monday to Saturday
Council is undertaking roadworks along Cape Cleveland Road between Babingtonia Road and the Australian Institute of Marine Science, Cape Cleveland.
This project is part of Council’s annual Roadwork program, which aims to maintain our Council-controlled road network to ensure the community’s transportation needs are adequately met and continue to support the growth of our region.
As part of this project, Council will:
- rehabilitate a portion of the associated road directly over the culvert
- reinforce the area using the slope stabilisation method to prevent further material loss
- remove vegetation within the works area as required.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor delays, and reduced speed limits.
Fulham Road & Charles Street, Heatley – Fulham Road, Heatley
Date published: Friday 28 March 2025
Work boundaries: Fulham Road and Charles Street, Heatley
Estimated start: Saturday 5 April 2025
Expected duration: Three (3) weeks
Normal work hours: Works will include night and day shifts to minimise impact on road users. Usual hours for the night shift between 6pm – 6am and day shift between 6am – 6pm.
Council is undertaking roadworks along Fulham Road between Mill Drive and Charles Street and on Charles Street between Fulham Road and Fitzroy Street, Heatley.
This project is part of Council’s annual Roadworks program, which aims to maintain our Council-controlled road network.
Works will include:
- resurfacing the Fulham Road and Mill Drive Roundabout in two (2) nights
- resurfacing the Charles Street and Fitzroy Roundabout in one (1) night
- resurfacing Fulham Road between Mill Drive and Charles Street in three (3) days
- resurfacing Charles Street between Fulham Road and Fitzroy Street in two (2) days.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits
- local traffic and residents will be guided to their residence by on-site traffic control.
This project is proudly funded by the Queensland Government through the Transport Infrastructure Development Scheme program and delivered in partnership with Council.
Webb Drive, Mount St John – Webb Drive, Mount St John
Date published: Monday 10 March 2025
Work boundaries: Webb Drive, Mount St John
Estimated start: Monday 24 March 2025
Expected duration: Two (2) weeks
Normal work hours: Where possible, works are planned for nights (6pm – 6am). Where required, some work will occur in mornings (6am – 8am)
Council is undertaking roadworks along Webb Drive between number 34 Webb Drive and Toll Street, Mount St John.
This project is part of Council’s annual Roadworks program, which maintains Council’s road network to ensure transportation needs are adequately met and continue to support the growth of our region.
As part of this project, Council will:
- remove the surface of one lane each night, followed by sealing the following morning (6am – 8am)
- lay new asphalt in the nights following the sealing
- complete line markings and finishings on asphalt the following week.
Businesses and customers travelling through the area may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including:
- lane closure for approximately one hour during the period of 6am – 8am for road sealing
- reduced speed limits and minor delays during this period.
Council will strive to accommodate driveway access requirements during works where possible. Please talk to the on-site crew leader if access is required during work hours.
This project is proudly funded by the Queensland Government through the Transport Infrastructure Development Scheme program and delivered in partnership with Townsville City Council.
Trees
Oonoonba Road, Idalia – Tree Removal Maintenance
Date published: Monday 7 April 2025
Work boundaries: Oonoonba Road, Idalia
Estimated start: Monday 14 April 2025
Expected duration: Three (3) days
Normal work hours: 6am to 6pm Monday to Saturday
Council’s Principal Arborist has recently completed a detailed inspection of a group of trees on the nature strip of Oonoonba Road between Lakeside Drive and River Boulevard in Idalia.
The decision to remove these trees was based on the certified arborist’s report, which confirms that they are in poor health due to recent weather events, making them a risk to surrounding infrastructure and community safety.
Additionally, maintenance will be performed on the vegetation along the fence line to restore the hedge to its original height, addressing ongoing maintenance concerns.
Works will include the removal of the trees and mulching. Suitable replacement trees will be planted near the removed trees to
replace the equivalent lost canopy cover.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Riverside Boulevard, Douglas – Tree Maintenance
Date published: Friday 28 March 2025
Work boundaries: Riverside Boulevard, Douglas
Estimated start: Monday 7 April 2025
Expected duration: Two (2) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Council’s Principal Arborist has recently conducted an inspection of all trees located near streetlights along Riverside Boulevard, specifically between Angus Smith Drive and Windarra Avenue, Douglas.
Maintenance work will be carried out on all designated trees. This includes the removal of identified tree branches and associated foliage to prevent them from obstructing streetlights or falling onto the roadway and pedestrian walkways.
Works will include the removal of the tree branches and mulching. Council arborists will oversee complete landscape maintenance to ensure the health and growth of the trees, preventing further damage to infrastructure and community safety.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Recently Completed
Location | Works | Description |
---|---|---|
Riverside Boulevard, Douglas | Raised Platforms Installation | Installed raised platforms. |
Bayswater Road, Hyde Park | Bayswater Road, Hyde Park | Completed roadworks. |
Francis Street, West End | Roadworks | Kerb and channels works. |
Flinders Street, Townsville City | Flinders Street, Townsville City | Closed road for event. |
Ogden Street, Townsville City | Roadworks | Completed roadworks along Ogden Street between Denham Street and Stokes Street within Townsville City. |
Rowes Bay and Pallarenda Beach Foreshore, Pallarenda | Coastal Management Recovery Works | Reshaped sand to mitigate effects of erosion. |
Empress Close, Cungulla | Coastal Works | Completed coastal works. |
Cooldetta Street, Cungulla | Coastal Works | Completed coastal works. |
Industrial Avenue, Bohle | Roadworks | Roadworks along Industrial Avenue. |
Saunders Beach Rest Area, Saunders Beach | Turtle Friendly Lighting Trial | Turtle Friendly Lighting Trial |
Muntalunga Drive, Nome | Muntalunga Drive, Nome | Tree Removal |
Tobruk Memorial Pools, The Strand, Townsville City | Tree Removal | Tree Removal |
4-46 Waterview Drive, Bushland Beach, Townsville City | Coastal Drone Survey | Surveyed coastal erosion. |
Riverway Drive from Allambie Lane to Jennifer Street, Kelso | Water Mains | Replace an aging water main along the footpath of the eastern side of Riverway Drive. |
Cobb Court, Annandale | Roadworks | Roadworks. |
Kern Brothers Drive, Kirwan | Roadworks | Roadworks. |
Pedestrian Bridge, Alma Bay | Pedestrian Bridge Deck Removal | Alma Bay Pedestrian Bridge Deck removed. |
65-73 West Point Road, Picnic Bay | Environmental Site Investigation | Environmental site investigation performed. |
Ogden Street, Townsville City | Ogden Street Roadworks – Stage Two | Completed Stage 2 of roadworks along Ogden Street between Denham Street and Stokes Street within Townsville City. |
Ogden Street, Townsville City | Ogden Street Roadworks – Stage One | Completed Stage 1 of roadworks along Ogden Street between Denham Street and Stokes Street within Townsville City. |